Import a programme and set the baseline

Bring an external programme in from an exchange file, check the calendars and links survived the trip, set the accepted programme as the baseline and publish it so progress is measured against something fixed.

4 bước10 phútNhà thầu chínhQuản lý dự án / thi côngNhà thầu phụ chuyên ngành

Cách hoạt động, từng bước một

4 bước xuyên suốt nền tảng - bạn làm gì ở mỗi bước và vì sao điều đó quan trọng.

1

Import the programme

Lịch trình nâng cao

Import the programme from its exchange file so the activities, durations, logic links and WBS come across without being rekeyed line by line.

Tại sao: Retyping a programme of a few hundred activities loses the logic that makes it a programme. Importing keeps the network intact so the critical path is real, not redrawn from memory.

Đầu vàoProgramme exchange fileĐầu raImported activities
2

Check what came across

Lịch trình nâng cao

Confirm the calendars, the logic links and the WBS survived the import, and that the completion date matches the source, before anyone trusts a date on it.

Tại sao: Exchange files drop constraints and remap calendars silently. Catching a shifted completion date now is far cheaper than discovering the imported programme was wrong three months in.

Đầu vàoImported activitiesCalendars and linksĐầu raChecked programme
3

Set the baseline

Tiến độ 4D

Freeze the agreed programme as the baseline, the fixed reference the job will be measured against for the rest of its life.

Tại sao: The baseline is the promise. Without a frozen one there is nothing to compare progress to, and every slippage argument becomes a matter of opinion instead of a matter of record.

Đầu vàoChecked programmeĐầu raFixed baseline
4

Publish it for tracking

Tiến độ

Publish the baseline so the team records progress against it and the planned-versus-actual picture builds from day one.

Tại sao: A baseline nobody tracks against is a wall decoration. Publishing it turns the programme into a live control that warns you early rather than a document reviewed after the fact.

Đầu vàoFixed baselineĐầu raProgress tracking on