Issue a tender addendum and reissue

A bidder query or a design change lands mid-tender. Capture it, draft the addendum, reissue it to every bidder on the same terms and confirm they all have it before the clock runs out.

4단계9 분종합건설사원가 컨설턴트 / 적산사PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 4단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Capture what forces it

Correspondence

Log the bidder question or the design change that makes the issued information wrong or incomplete, and decide whether it needs a formal addendum to all or a private answer to one.

이유: The moment a query changes the scope, everyone needs to know. Capturing the trigger cleanly is what stops a helpful side conversation turning into an unfair advantage.

입력Bidder queryDesign change결과Logged trigger
2

Draft the addendum

문서

Write the addendum with a clear number, the change it makes, the documents it supersedes and the revised files attached, so a bidder can act on it without guessing.

이유: A numbered addendum with the superseded documents named is what keeps the tender set unambiguous. Loose emails leave firms pricing off different revisions of the same drawing.

입력Logged triggerRevised documents결과Numbered addendum
3

Reissue to every bidder

입찰

Send the addendum to the whole bidder list at once and, if the change is material, extend the submission deadline so nobody is squeezed for the time to reprice.

이유: Issuing to all on the same day and the same terms is the heart of a fair tender. Extending the deadline where it matters keeps the prices sharp instead of rushed.

입력Numbered addendumBidder list결과Reissued to allReset deadline
4

Confirm every bidder has it

입찰

Track that each bidder acknowledged the addendum, and chase the ones who have not, so no firm submits against out-of-date information.

이유: A bid priced without the latest addendum is worthless and has to be rejected. Confirming receipt from all is the cheap step that protects the whole exercise.

입력Reissued addendum결과Acknowledged by all