Price the preliminaries and general conditions
Price the cost of running the job itself - site staff, welfare, plant, scaffolding and insurances - split into time-related and fixed and driven by the programme, then carry it into the bill.
Хэрхэн ажилладаг, алхам алхмаар
Платформ даяар 4 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.
List the prelims scope
Ерөнхий зардалBuild the list of everything it takes to run the site: management and supervision, welfare and cabins, temporary services, common plant, scaffolding, security, insurances and bonds.
Яагаад: The items you forget in prelims are the ones you fund out of profit. A complete checklist read against the contract is the difference between a covered site and a leaking one.
Split time-related from fixed
Ерөнхий зардалMark each item as time-related or fixed, then price the time-related ones per week against the programme duration and the fixed ones as one-off set-up and removal.
Яагаад: Splitting them this way is what lets prelims flex if the programme moves. If the job runs four weeks late, you can show exactly what the extra time costs instead of guessing.
Check the resources roll up
Нөөцийн нэгтгэлLook at the staff, plant and cabins the prelims imply in the resource summary and sanity check the headcount curve against the programme peaks.
Яагаад: A prelims price that needs three site managers in a quiet month is a warning. Seeing the resource curve catches a double count or a gap before it reaches the tender total.
Carry it into the bill
Ажил материалын жагсаалтBring the prelims total into the bill as its own section, kept separate from measured work, and read it back as a percentage of the works value.
Яагаад: Keeping prelims visible as their own line lets a reviewer benchmark them at a glance. Burying them in the rates hides the one number a client always wants to test.