Price the preliminaries and general conditions

Price the cost of running the job itself - site staff, welfare, plant, scaffolding and insurances - split into time-related and fixed and driven by the programme, then carry it into the bill.

4ステップ11 分総合建設会社コストコンサルタント / 積算士プロジェクト / 施工管理者

仕組みをステップごとに

プラットフォーム全体で4ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

List the prelims scope

共通仮設費

Build the list of everything it takes to run the site: management and supervision, welfare and cabins, temporary services, common plant, scaffolding, security, insurances and bonds.

理由: The items you forget in prelims are the ones you fund out of profit. A complete checklist read against the contract is the difference between a covered site and a leaking one.

入力Contract & prelimsOutline programme出力Prelims schedule
2

Split time-related from fixed

共通仮設費

Mark each item as time-related or fixed, then price the time-related ones per week against the programme duration and the fixed ones as one-off set-up and removal.

理由: Splitting them this way is what lets prelims flex if the programme moves. If the job runs four weeks late, you can show exactly what the extra time costs instead of guessing.

入力Prelims scheduleProgramme duration出力Priced prelims
3

Check the resources roll up

リソース集計

Look at the staff, plant and cabins the prelims imply in the resource summary and sanity check the headcount curve against the programme peaks.

理由: A prelims price that needs three site managers in a quiet month is a warning. Seeing the resource curve catches a double count or a gap before it reaches the tender total.

入力Priced prelims出力Resource roll-up
4

Carry it into the bill

数量明細書

Bring the prelims total into the bill as its own section, kept separate from measured work, and read it back as a percentage of the works value.

理由: Keeping prelims visible as their own line lets a reviewer benchmark them at a glance. Burying them in the rates hides the one number a client always wants to test.

入力Priced prelimsMeasured works出力Prelims bill sectionPrelims as percent of works