Price the preliminaries and general conditions

Price the cost of running the job itself - site staff, welfare, plant, scaffolding and insurances - split into time-related and fixed and driven by the programme, then carry it into the bill.

4 koraka11 minGlavni izvođačKonzultant za troškove / QSVoditelj projekta / gradnje

Kako funkcionira, korak po korak

4 koraka kroz platformu - što radite u svakom i zašto je važno.

1

List the prelims scope

Pripremni radovi

Build the list of everything it takes to run the site: management and supervision, welfare and cabins, temporary services, common plant, scaffolding, security, insurances and bonds.

Zašto: The items you forget in prelims are the ones you fund out of profit. A complete checklist read against the contract is the difference between a covered site and a leaking one.

UlazContract & prelimsOutline programmeRezultatPrelims schedule
2

Split time-related from fixed

Pripremni radovi

Mark each item as time-related or fixed, then price the time-related ones per week against the programme duration and the fixed ones as one-off set-up and removal.

Zašto: Splitting them this way is what lets prelims flex if the programme moves. If the job runs four weeks late, you can show exactly what the extra time costs instead of guessing.

UlazPrelims scheduleProgramme durationRezultatPriced prelims
3

Check the resources roll up

Sažetak resursa

Look at the staff, plant and cabins the prelims imply in the resource summary and sanity check the headcount curve against the programme peaks.

Zašto: A prelims price that needs three site managers in a quiet month is a warning. Seeing the resource curve catches a double count or a gap before it reaches the tender total.

UlazPriced prelimsRezultatResource roll-up
4

Carry it into the bill

Troškovnik

Bring the prelims total into the bill as its own section, kept separate from measured work, and read it back as a percentage of the works value.

Zašto: Keeping prelims visible as their own line lets a reviewer benchmark them at a glance. Burying them in the rates hides the one number a client always wants to test.

UlazPriced prelimsMeasured worksRezultatPrelims bill sectionPrelims as percent of works