Price the preliminaries and general conditions

Price the cost of running the job itself - site staff, welfare, plant, scaffolding and insurances - split into time-related and fixed and driven by the programme, then carry it into the bill.

4 个步骤11 分钟总承包商造价咨询 / 工料测量师项目/施工经理

运作方式,逐步说明

贯穿平台的 4 个步骤 - 每一步做什么,以及为什么重要。

1

List the prelims scope

措施项目费

Build the list of everything it takes to run the site: management and supervision, welfare and cabins, temporary services, common plant, scaffolding, security, insurances and bonds.

原因: The items you forget in prelims are the ones you fund out of profit. A complete checklist read against the contract is the difference between a covered site and a leaking one.

输入Contract & prelimsOutline programme成果Prelims schedule
2

Split time-related from fixed

措施项目费

Mark each item as time-related or fixed, then price the time-related ones per week against the programme duration and the fixed ones as one-off set-up and removal.

原因: Splitting them this way is what lets prelims flex if the programme moves. If the job runs four weeks late, you can show exactly what the extra time costs instead of guessing.

输入Prelims scheduleProgramme duration成果Priced prelims
3

Check the resources roll up

资源汇总

Look at the staff, plant and cabins the prelims imply in the resource summary and sanity check the headcount curve against the programme peaks.

原因: A prelims price that needs three site managers in a quiet month is a warning. Seeing the resource curve catches a double count or a gap before it reaches the tender total.

输入Priced prelims成果Resource roll-up
4

Carry it into the bill

工程量清单

Bring the prelims total into the bill as its own section, kept separate from measured work, and read it back as a percentage of the works value.

原因: Keeping prelims visible as their own line lets a reviewer benchmark them at a glance. Burying them in the rates hides the one number a client always wants to test.

输入Priced prelimsMeasured works成果Prelims bill sectionPrelims as percent of works