Price the preliminaries and general conditions

Price the cost of running the job itself - site staff, welfare, plant, scaffolding and insurances - split into time-related and fixed and driven by the programme, then carry it into the bill.

4 चरण11 मिनटमुख्य ठेकेदारलागत सलाहकार / QSप्रोजेक्ट / निर्माण प्रबंधक

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 4 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

List the prelims scope

प्रारंभिक कार्य

Build the list of everything it takes to run the site: management and supervision, welfare and cabins, temporary services, common plant, scaffolding, security, insurances and bonds.

क्यों: The items you forget in prelims are the ones you fund out of profit. A complete checklist read against the contract is the difference between a covered site and a leaking one.

इनपुटContract & prelimsOutline programmeपरिणामPrelims schedule
2

Split time-related from fixed

प्रारंभिक कार्य

Mark each item as time-related or fixed, then price the time-related ones per week against the programme duration and the fixed ones as one-off set-up and removal.

क्यों: Splitting them this way is what lets prelims flex if the programme moves. If the job runs four weeks late, you can show exactly what the extra time costs instead of guessing.

इनपुटPrelims scheduleProgramme durationपरिणामPriced prelims
3

Check the resources roll up

संसाधन सारांश

Look at the staff, plant and cabins the prelims imply in the resource summary and sanity check the headcount curve against the programme peaks.

क्यों: A prelims price that needs three site managers in a quiet month is a warning. Seeing the resource curve catches a double count or a gap before it reaches the tender total.

इनपुटPriced prelimsपरिणामResource roll-up
4

Carry it into the bill

मात्रा विवरण

Bring the prelims total into the bill as its own section, kept separate from measured work, and read it back as a percentage of the works value.

क्यों: Keeping prelims visible as their own line lets a reviewer benchmark them at a glance. Burying them in the rates hides the one number a client always wants to test.

इनपुटPriced prelimsMeasured worksपरिणामPrelims bill sectionPrelims as percent of works