Agree the final account and release retention

Close the contract cleanly: settle the final account from the agreed variations and valuations, release the retention that is due, and report the outturn against budget.

3 koraka9 minGlavni izvođačKonzultant za troškove / QSSpecijalizirani podizvođač

Kako funkcionira, korak po korak

3 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Build the final account

Ugovori

Pull the agreed variations and the certified valuations into one final account, settle the last few open items, and confirm the total both sides are signing up to.

Zašto: A final account assembled from loose emails is one nobody trusts to sign. Building it from the variations and valuations already agreed is what turns a negotiation into a number everyone can accept.

UlazAgreed variationsCertified valuationsRezultatFinal account totalOutstanding items
2

Release the retention due

Financije

Against the agreed account, release the retention that has fallen due now the defects are cleared, and set the final payment, keeping back only what a live defect still justifies.

Zašto: Retention sat on past its release date is the subcontractor's money you are holding for no reason, and it poisons the next tender. Releasing it on time is fair, and it is what gets you a keen price next round.

UlazFinal account totalRetention heldRezultatRetention releaseFinal payment
3

Report the outturn against budget

Izvješća

Run the report that sets the settled final account against the budget you started with, break down where the money moved, and file it as the closing position on the job.

Zašto: A job closed with no outturn report teaches you nothing for the next one. Setting final against budget is how you see which trades and variations drove the result and price the next project sharper.

UlazFinal account totalOriginal budgetRezultatOutturn reportVariance breakdown