Invoice construction work under inversion del sujeto pasivo

Work out where you sit in the chain, record the determination against the invoice with the article it rests on, issue the invoice with the statutory sentence and no VAT, keep the confirmation that made it apply and report it inside the four days the authority allows.

5 steps15 minSpecialist subcontractorGeneral contractorCost consultancy / QS practice

How it works, step by step

5 steps across the platform - what you do at each one, and why it matters.

1

Establish where you sit and what you are building

Contracts

Read the contract for two facts: that there is a contract between a promotor and a contratista for the construction or refurbishment of a building, and that your own contract sits under it, directly or through another subcontract. Both have to hold before the reverse charge reaches your invoice.

Why: The rule is about the chain, not about the trade. The same crew doing the same work is inside it on a refurbishment under a main contract and outside it on a call-out repair for the same client, and nobody notices the difference until an inspection reads the two invoices side by side.

InContract and subcontract chainDescription of the worksOutYour position in the chainWhether the works are in scope
2

Record the determination against the invoice

Withholding Tax

Create the determination for this invoice: the Spanish construction rule, the article it rests on, the sentence that goes on the document, the net amount and the fact that the buyer accounts for the VAT. The record will not leave draft while the wording is missing or a VAT amount is still sitting on it.

Why: Per invoice rather than per customer, because the same customer can be inside the rule on one job and outside it on the next. Recorded rather than remembered, because the question that arrives in an inspection is why this invoice carried no VAT, and the answer has to be a decision with a date and an article rather than a habit.

InYour position in the chainNet amount to be invoicedOutDetermination on recordStatutory wording on the invoice
3

Issue it with the sentence on and the VAT off

Finance

Raise the invoice for the net amount, put the statutory sentence naming the article on the face of it, and leave the VAT line empty rather than at zero percent. Reference the certificacion it answers so the two can be matched later.

Why: An invoice with the right total and no sentence is the one that gets returned, and returning it restarts the payment clock that was the whole point of certifying on time. A zero-rate line is not the same thing as no VAT either: it says a rate was applied, which is a different tax position from the one you meant.

InDetermination on recordApproved certificacionOutInvoice with no VAT amountRequired sentence on the document
4

Keep the confirmation that made it apply

Documents

File the customer's written statement that they are acting as a business in this transaction, together with their tax registration details, and link it to the invoices it covers. Keep it against the contract it was given for rather than against the customer, because the same customer can be outside the rule on the next job.

Why: The rule turns on the customer's status, and the customer is the only one who can state it. Without that statement on file the VAT you did not charge is VAT you may end up paying yourself, with the interest, years after the client has gone.

InCustomer confirmed in writingTax registration recordOutFiled evidence documentEvidence linked to the invoice
5

Report it inside the four days

E-invoice Clearance

Send the invoice record to the authority under the Spanish reporting regime and keep the acknowledgement reference against it. The invoice is valid from the moment it is issued; the report is a separate obligation with a four calendar day window, and a correction is an annulment record followed by a corrected one.

Why: Late reporting is a penalty rather than an invalid invoice, which is exactly why it slides: nothing breaks and nobody chases it. It is also the cheapest thing on this list to keep on top of, because the window is short enough that either you have a routine or you have a fine.

InIssued invoiceOutInvoice reported to the authorityAcknowledgement reference on record
Modules

Modules in this playbook

5 / 190 platform modules

The market this case is written for

Spain

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.