Keep a daily report that survives a claim

Write the day from yesterday's report, book the crew against cost codes, record equipment worked, idle and down, leave no day unaccounted for, and hand the finished record to the claim that needs it.

6 steps16 minGeneral contractorSpecialist subcontractorProject / construction management firm

How it works, step by step

6 steps across the platform - what you do at each one, and why it matters.

1

Start today's report from yesterday's, not from a blank page

Daily Diary

Open the site diary and create today from the previous day. The crews, areas and activities carry over, so the work is editing what changed rather than typing the whole day again: who is on which area, what got done, what stopped.

Why: A blank form at the end of a long day gets three words in it. A form that already reads like yesterday gets corrected, and a corrected form is a real record. This is the whole difference between a diary that is kept and one that exists in the contract only.

InYesterday's reportWho turned up todayOutToday's report, writtenAuthor and time on record
2

Book the crew's hours against the work, not against the week

Field Time

Put the day's hours in field time against the cost code they were worked on, and mark separately any hours that were time and materials rather than measured work. Where a crew split across two areas, split the hours rather than rounding them to whichever area was bigger.

Why: Hours booked to a cost code are hours you can defend later at a rate. Hours booked to a week are payroll and nothing else. When a change is priced on actual labor, this is the only record that tells you what the labor actually was.

InCrew on site todayCost codes for the workOutHours booked to cost codesTime and materials work flagged
3

Record equipment in three states, and say what the weather stopped

Daily Diary

For each machine on site record the hours it worked, the hours it stood idle and the hours it was down, rather than a single mark that it was present. Then record the weather with the thing it prevented: not just rain, but which pour was called off and which crew stood.

Why: Idle plant is a cost you can claim and down plant is a cost you cannot, and only the report written on the day can tell them apart. Weather recorded on its own proves the weather happened, which nobody disputes; weather recorded against the activity it stopped is what proves the delay.

InEquipment on siteWeather and ground conditionsOutEquipment worked, idle and downWhat the conditions stopped
4

Close the calendar so there is no day without an answer

Daily Diary

Review the period as a run of days rather than as a list of reports, and give the empty ones an explicit reason: weekend, holiday, shutdown, weather, no access. A day with no work is still a day that gets a report saying so.

Why: Federal construction reporting asks for every calendar day to be accounted for, and a missing day is read as a record that was not kept rather than as a day nothing happened. The other side does not have to prove what was in the gap, only that the gap is there.

InThe period being reportedReports written so farOutEvery calendar day accounted forNo-work days given a reason
5

Bind the days to the event they are going to have to prove

Claims Evidence

In claims evidence, collect the days that bear on one event into a single bundle with the photos, instructions and correspondence that belong to them, and put them in the order they happened.

Why: Evidence assembled while the job is running takes an hour. The same evidence assembled from an archive after the job closed takes a week and comes back incomplete, because the people who knew which photo belonged to which day have moved on.

InThe days in questionPhotos and correspondenceOutEvidence bound to the eventTimeline a reader can follow
6

Turn the record into a priced change

Variations

Raise the variation from the bundle so the labor, plant and material on it come from the hours and equipment states already booked, rather than from an estimate made after the fact.

Why: A number that can be walked back to a specific day, a specific crew and a specific machine gets argued about on its merits. A number that cannot gets treated as a negotiating position, and negotiating positions get halved.

InThe evidence bundleBooked hours and plant timeOutA priced change, not an assertionEach cost traceable to a day
Modules

Modules in this playbook

4 / 184 platform modules

More in Site & field

Site & field

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 steps9 minOpen
Site & field

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 steps9 minOpen