Открыть демо
Кейсы / Сметы и калькуляция
Сметы и калькуляция

Manage provisional sums and allowances

Handle the parts of a bill the design cannot yet fix - provisional sums, prime cost sums and allowances - kept separate from measured work so each one has an owner and can be drawn down cleanly.

Шагов: 410 минСметный консультант / QSГенеральный подрядчикДевелопер / заказчик

Как это работает, шаг за шагом

4 шагов через всю платформу - что делать на каждом и почему это важно.

1

Find what cannot be fixed yet

Резервы и непредвиденные затраты

Go through the scope and list every element the design cannot yet price firmly: undesigned finishes, a specialist package still out to market, statutory connections, a prime cost item.

Зачем: Naming the soft spots up front is what stops them being priced twice or missed entirely. It also tells the client exactly which parts of the number are still to be firmed up.

На входеIncomplete designScope gapsНа выходеList of sums
2

Set the type and the basis

Резервы и непредвиденные затраты

Mark each one as a defined or undefined provisional sum, a prime cost sum or an allowance, then record the basis behind the figure and who owns firming it up.

Зачем: A defined sum carries programme and preliminaries; an undefined one does not. Getting the type right now decides whether you can claim time and cost when it is finally instructed.

На входеList of sumsНа выходеBasis and owner set
3

Carry them into the bill

Ведомость объёмов работ

Bring the sums into the bill in their own section, clearly separate from measured work, so the tender total shows firm price and provisional money apart.

Зачем: Kept separate, the sums can be expended and adjusted through the job without disturbing the measured rates. Buried in the rates they become impossible to track or hand back.

На входеClassified sumsНа выходеSeparate bill section
4

Check for double counting

Проверка

Validate that nothing sits in both a rate and a provisional sum, that every sum has an owner, and that the totals reconcile before the bill goes out.

Зачем: Double counting a package is an easy way to price yourself out of a job; missing it is an easy way to lose money. A quick validation pass closes both traps at once.

На входеBill with sumsНа выходеNo double counts

Ещё в разделе Сметы и калькуляция