Bill the month with a payment application

Agree a schedule of values against the contract sum, bill the period on a continuation sheet with stored materials and retainage, and issue a certificate face whose arithmetic the owner's accountant can follow.

7 steps16 minGeneral contractorSpecialist subcontractorProject / construction management firm

How it works, step by step

7 steps across the platform - what you do at each one, and why it matters.

1

Break the contract sum into a schedule of values

Contracts

On the contract, enter the schedule of values line by line from the priced bill: an item number, a description the owner will recognise, and a scheduled value. Check that the lines add up to the contract sum exactly before you bill anything against them.

Why: Every later application is measured against these lines, so a schedule that does not tie to the contract sum poisons every month that follows. This is also the page an owner's representative reads for front-loading, which is the fastest way to have a first application sent back.

InSigned contract and sumPriced bill or breakdownOutSchedule of valuesLine total tied to contract sum
2

Record the retainage the contract actually holds

Contracts

Set the retainage percentage on the contract from the executed agreement, and name the event that releases it. Do this from the contract wording rather than from what the last job did.

Why: Retainage is the largest single deduction on the application and the one most often carried over from a previous job by habit. A rate that is half a point wrong is a five figure argument on a mid-size contract, and it repeats every month until someone notices.

InPayment terms in the contractSchedule of valuesOutRetainage rate on recordRelease event named
3

Open the application for the period and bill the work done

Contracts

Raise the application for this billing period and go down the schedule of values entering what was completed in the period and what material is on site or stored off site but not yet installed. Work billed in earlier periods is already carried forward for you.

Why: Stored material is the line owners scrutinise hardest, because it is money for something that is not yet built. Keeping it in its own column, rather than folded into work completed, is what makes it defensible instead of arguable.

InWork completed this periodMaterials presently storedOutApplication for the periodPeriod start and end on record
4

Fold the approved change orders into the contract sum

Contracts

Check that every change order approved before the period end is reflected, so the application shows the original contract sum, the net change by change orders and the adjusted contract sum as three separate figures.

Why: An application that bills changed work against an unchanged contract sum reads as an overbill, and it will be certified down. Showing the three figures separately is what lets the owner agree the change and the billing in one pass instead of two.

InApproved change ordersOriginal contract sumOutAdjusted contract sumNet change by change order
5

Read the certificate face and check it ties

Contracts

Open the payment application view and read the summary the owner will read: total completed and stored to date, retainage on work and on stored material, total earned less retainage, less previous certificates, current payment due, balance to finish. Every figure is built from the lines you just entered, so check the total earned against the continuation sheet and the previous certificates figure against what was actually certified.

Why: Applications are rejected on arithmetic far more often than on merit. A summary that is derived from the lines rather than typed beside them is the difference between one review cycle and three.

InCompleted continuation sheetPreviously certified totalOutCurrent payment dueBalance to finish
6

Issue the application and log the date it went out

Contracts

Export the application as a PDF, submit it, and let the contract record the date it was submitted. The application then moves through submitted, certified and paid as the owner acts on it.

Why: Prompt payment clocks in most states start from a dated submission, not from a conversation. The dated record is also the first thing anyone asks for when a payment is late.

InChecked applicationOwner or architect of recordOutApplication PDFSubmission dated and logged
7

Watch the money against what you billed

Finance

In finance, read the job against the applications: billed, certified, received, and the retainage held to date across every period. Anything certified and not received is what your next call is about.

Why: The application is only half the cycle. A contractor who knows on the day that a certified application has not been paid, and by how much, is running the job. One who finds out at month end is funding the owner.

InCertified applicationPayments receivedOutCash position for the jobRetainage held to date
Modules

Modules in this playbook

2 / 184 platform modules

More in Commercial & contracts

Commercial & contracts

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 steps11 minOpen