Level bids to a common scope

Normalise structurally different bids - filling the scope gaps and pricing the qualifications - so every offer sits on the same basis before you compare the bottom lines and pick the real lowest.

4 个步骤12 分钟总承包商造价咨询 / 工料测量师项目/施工经理

运作方式,逐步说明

贯穿平台的 4 个步骤 - 每一步做什么,以及为什么重要。

1

Collect the bids

投标管理

Gather every returned bid with the covering letter, the priced schedule and the qualifications each firm attached, so nothing that conditions a price is left in an inbox.

原因: The qualifications are where the real differences hide. A bid read without its conditions is a number without a meaning, and half the leveling work is just finding them.

输入Returned bidsQualifications成果Bid set assembled
2

Map each bid to the scope

投标管理

Set each bid against the common scope and flag what is missing, what is extra and where a firm has priced something different from what was asked.

原因: A gap you spot now is a negotiation; a gap you miss becomes a variation the day after award. Mapping to a single scope is what turns apples and oranges back into apples.

输入Bid setCommon scope成果Scope gaps flagged
3

Adjust to one basis

投标管理

Price the gaps and the qualifications into each bid as adjustments, so every offer is restated as what it would cost to deliver the full common scope.

原因: Adjusting rather than disqualifying keeps a strong contractor in the race even if their bid was scrappy. It is the fairest and the sharpest way to find the true lowest cost.

输入Scope gaps成果Levelled bids
4

Compare and recommend

招投标

Compare the levelled bids against each other and the budget, then write the recommendation on the offer that is genuinely lowest for the full scope, not just cheapest on paper.

原因: A recommendation built on levelled numbers survives challenge. It shows the client you compared like for like and awarded on value rather than on whoever forgot the most.

输入Levelled bidsBudget baseline成果Award recommendation