Run a three-way match before paying a supplier

Only pay for what you ordered and received: line the invoice up against the purchase order and the goods received note, resolve the differences, then release the payment.

3단계8 분종합건설사전문건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 3단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Pull the order and the receipt

조달

Open the purchase order and its goods received note so you have, side by side, what you agreed to buy at what price and what actually turned up on site.

이유: The invoice is only one of three documents that have to agree. Pulling the order and the receipt first is what gives you something honest to check the supplier's bill against.

입력Purchase orderGoods received note결과Ordered quantitiesReceived quantities
2

Match the invoice against both

사건 대사

Line the invoice up against the order and the receipt, pass the lines where price and quantity agree on all three, and flag any short delivery, price creep or item you never ordered.

이유: A three-way match is the check that catches the invoice for forty units when thirty arrived. Doing it before payment is far cheaper than clawing money back from a supplier afterwards.

입력Supplier invoiceOrdered and received quantities결과Matched linesFlagged discrepancies
3

Release only the matched payment

재무

Release payment for the lines that matched, hold back the flagged ones until the supplier explains or credits them, and record why anything was held so the query has a trail.

이유: Paying the whole invoice to avoid the hassle of a query is how the leaks add up. Releasing only what matched keeps the pressure on the supplier to fix their bill and keeps your cost honest.

입력Matched linesApproved value결과Approved paymentHeld queries