Guided playbooks

293 construction playbooks, ready to run.

End-to-end workflows for estimating, tendering, BIM, site work, commercial control and handover. Each one is a worked example you can open in the live demo and follow step by step, with what to do and why at every stage. 140 of them apply in any country; 153 are written for 15 markets, 10 each except Germany with 13.

293 playbooks8 disciplines1435 guided stepsOpen any one in the live demo
Worked example

Run a tender from a bill of quantities, with the numbers

The demo project is a supermarket in Karlsruhe with a bill of 16 sections and a grand total of EUR 9,600,000 net. All names and figures are fictional. This playbook takes one section of that bill, refrigeration (DIN 276 cost group 470), through to an award. Every figure below is read from the demo data.

  1. Open the priced bill

    Section LV 15 has 20 positions in two subsections. Each position is quantity times unit rate, and the section adds up to EUR 980,000.00 net, exactly its budget.

    OZDescriptionUnitQtyUnit rate EURTotal EUR
    15.01.0010Transcritical CO2 booster rack with parallel compression, 120 kW coolinglump sum1145,000.00145,000.00
    15.01.0020Gas cooler on the roof incl. steel frame and vibration dampingpcs121,400.0021,400.00
    15.01.0030Heat recovery, 2-stage (desuperheater + condenser) up to 150 kW thermallump sum129,800.0029,800.00
    15.01.0040CO2 pipework, K65 / stainless steel, incl. insulation and bracketsm52098.0050,960.00
    15.01.0050Medium-temperature cold room +2 C, approx. 60 m2, PU 100 mm, incl. doorpcs116,400.0016,400.00
    15.01.0060Fruit and vegetable cold room +8 C, approx. 32 m2, PU 80 mmpcs19,400.009,400.00
    15.01.0070Freezer room -22 C, approx. 40 m2, PU 150 mm, incl. floorpcs129,500.0029,500.00
    15.01.0080Air coolers / evaporators, CO2-rated, for the cold roomspcs63,100.0018,600.00
    15.01.0090Connection of display cabinets (client-supplied), piping and commissioningpcs181,200.0021,600.00
    15.01.0100CO2 gas detection, plant room and sales arealump sum18,400.008,400.00
    15.01.0110Refrigeration controls incl. remote monitoringlump sum115,400.0015,400.00
    15.01.0120Leak test, commissioning, acceptance to EN 378, instructionlump sum110,200.0010,200.00
    15.02.0010Medium-temperature cooling shelves, plug-less, glass doors, H = 2.0 m, ready to connectm605,050.00303,000.00
    15.02.0020Freezer cabinets with glass doors, rack connectionm286,500.00182,000.00
    15.02.0030Fresh-food service counter 8 m incl. connection to the compressor setm88,100.0064,800.00
    15.02.0040Cabinet controllers, sensors and bus cablingpcs32495.0015,840.00
    15.02.0050Defrost and condensate lines, insulated, to the main drainm22088.0019,360.00
    15.02.0060Noise protection and mounting frame for the racklump sum110,400.0010,400.00
    15.02.0070Maintenance contract year 1 incl. 24 h standbylump sum17,800.007,800.00
    15.02.0080CO2 first fill, leak certificate and 72 h trial run 1lump sum1140.00140.00
    15.01Subtotal 15.01 Plant376,660.00
    15.02Subtotal 15.02 Cabinets and service603,340.00
    Section LV 15 total, net980,000.00

    1 Each section of the demo bill ends with one small balancing position so that it closes exactly on its budget. A bill you price yourself has no such line.

    The demo bill of quantities in the editor
    The whole demo bill in the editor: sections, positions, quantities and the grand total.
  2. Check the bill before it goes out

    Run validation. The demo bill scores 96% and lists warnings, for example an unusually high unit rate. The report only flags; a person decides which positions to correct.

    Validation report of the demo bill
    Validation report of the demo bill with quality score and rule results.
  3. Create the tender package

    Package VP-07 takes section LV 15 as its scope, with a budget of EUR 980,000.00 net and a submission deadline. The package carries the same positions and quantities that every bidder prices.

    Tender packages of the demo project
    Tender packages of the demo project, with budgets and status.
  4. Collect the bids

    Three demo companies return a price for the package. The bill can go out without prices as Excel or GAEB X83, and the priced answer comes back as X84.

    BidderNet bid EURAgainst budget
    Bidder A958,400.00-2.2 %
    Bidder B1,012,600.00+3.3 %
    Bidder C1,058,900.00+8.1 %
  5. Level the bids and award

    The spread between the lowest and the highest bid is 10.5 %. The lowest bid is EUR 21,600.00 (2.2 %) under budget. In the demo the package is marked awarded to Bidder A.

The demo project installs with the app, so you can open the same section yourself under Projects, Bill of Quantities, LV 15.

I work asCountryMarkets
Planning & controls

Set up a project and hand it over

Take a job from the very first setup right through to handover. Create it, price the work,…

5 steps20 minOpen
Estimating & costing

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 steps8 minOpen
Tendering & procurement

Run a tender from a BOQ

Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…

5 steps12 minOpen
Tendering & procurement

Procure materials from the BOQ

Buy the quantities you already priced: raise a requisition off the bill, place the order wi…

4 steps10 minOpen
BIM & takeoff

Get 6D carbon from a BIM model

Turn a converted BIM model into an embodied carbon footprint. Auto-enrich reads quantities…

5 steps12 minOpen
Planning & controls

Build a baseline and track progress

Plan the programme, freeze a baseline to measure against, feed real progress back from site…

4 steps12 minOpen
BIM & takeoff

Get quantities from a BIM model

Load a converted model, lift the element quantities straight off the geometry, carry them i…

3 steps12 minOpen
BIM & takeoff

Measure quantities from a DWG

Load a DWG, lock the scale against a known dimension, measure the areas, lengths and counts…

3 steps10 minOpen
Site & field

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 steps9 minOpen
Quality & safety

Inspect work and close a non-conformance

Inspect the work against its acceptance criteria, raise a non-conformance the moment it fai…

3 steps10 minOpen
Commercial & contracts

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 steps11 minOpen
Commercial & contracts

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 steps11 minOpen
Handover & lifecycle

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 steps14 minOpen
Estimating & costing

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 steps12 minOpen
Estimating & costing

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 steps11 minOpen
Tendering & procurement

Compare bids and award

Take a folder of returned tenders that never quite match, strip them back to the same scope…

3 steps12 minOpen
Planning & controls

Earned value and forecast

See where the job truly stands against the plan and the budget: bring the programme current…

3 steps13 minOpen
BIM & takeoff

Coordinate models and resolve clashes

Bring the discipline models together on one coordinate base, run the clash test, clear the…

3 steps13 minOpen
Site & field

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 steps9 minOpen
Quality & safety

Toolbox talk and safety check

Brief the crew on the hazards this shift actually carries, capture who was there, then prov…

2 steps8 minOpen
Commercial & contracts

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 steps12 minOpen
Handover & lifecycle

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 steps12 minOpen
Commercial & contracts

Change register and impact

Capture every change in one register, read the time and cost impact scored against the real…

3 steps11 minOpen
Commercial & contracts

Issue an electronic invoice

Turn a certified valuation into a compliant electronic invoice, issue it in the structured…

3 steps10 minOpen
Planning & controls

Set up a new project

Stand up a new job so everything downstream has one clean spine to attach to: create the re…

3 steps8 minOpen
Estimating & costing

Build an assembly (recipe rate)

Turn a build-up you price again and again into one reusable assembly: pick the component it…

3 steps11 minOpen
Estimating & costing

Localize an estimate to a region

Move a priced estimate to another region without guessing: pick the regional cost base, app…

3 steps12 minOpen
Commercial & contracts

Forecast project cash flow

Spread the priced work across the programme to see cash in and cash out month by month, fin…

3 steps12 minOpen
Site & field

Capture daywork and time and materials

Turn instructed extra work into a claim that gets paid: record the labour, plant and materi…

3 steps9 minOpen
Handover & lifecycle

Run a handover acceptance inspection

Walk the finished works with the client, record what passes and what does not against the a…

3 steps11 minOpen
Commercial & contracts

Control cost against budget

Hold the job to its number: fix the priced bill as the budget baseline, track committed and…

3 steps12 minOpen
Quality & safety

Get a material submittal approved

Put the product you plan to buy in front of the designer with its data behind it, get it ch…

3 steps9 minOpen
Planning & controls

Compile the weekly progress report

Mark up where the programme actually is, gather the week of diary entries and photos that p…

3 steps10 minOpen
Site & field

Issue a controlled drawing revision

Register a new drawing revision, mark the old one superseded, transmit it to every trade th…

3 steps8 minOpen
Commercial & contracts

Run the cost-value reconciliation

Set the cost you have committed against the value you have earned to the same cut-off date,…

3 steps12 minOpen
Site & field

Report and action a near-miss

Log the near-miss while the detail is fresh, work out the cause and set the corrective acti…

3 steps8 minOpen
Estimating & costing

Sense-check an estimate against benchmarks

Hold a priced estimate up against the reference cost base and your own history, flag the ra…

3 steps10 minOpen
Planning & controls

Produce a short-interval lookahead

Pull the next two to three weeks off the master programme, clear the constraints sitting in…

3 steps10 minOpen
Estimating & costing

Build an elemental cost plan

Structure a cost plan by classified element rather than by trade, check it against the clas…

3 steps11 minOpen
Planning & controls

Balance crews and plant across the programme

Read the labour and plant the near-term programme actually needs, check it against what is…

3 steps10 minOpen
BIM & takeoff

Audit a model before it goes out

Run the checks that catch a bad model before a client or a site team opens it: coordinate b…

3 steps10 minOpen
Planning & controls

Review and mitigate the risk register

Walk the risk register on a regular cadence, score likelihood and impact honestly, and assi…

3 steps9 minOpen
Site & field

Run a toolbox talk and record attendance

Plan a short safety briefing for the day, high-risk activity, deliver it to the crew, captu…

5 steps9 minOpen
Planning & controls

Build the baseline programme

Turn the agreed scope and the priced BOQ into a baseline programme: list the activities, se…

5 steps12 minOpen
Planning & controls

Update the programme and reforecast

Take the actual progress the site reports, mark activities complete or part complete, let t…

5 steps11 minOpen
Tendering & procurement

Issue a procurement and buying schedule

Turn the BOQ and the programme into a buying schedule: list the packages to buy, set lead t…

5 steps11 minOpen
Commercial & contracts

Assess and price a variation

When a change is instructed, capture it, price the added or omitted work from your rates, c…

5 steps11 minOpen
Commercial & contracts

Prepare an interim payment application

Build the monthly interim application: measure the work done to date, value it against the…

5 steps10 minOpen
BIM & takeoff

Coordinate and resolve model clashes

Run a clash coordination round: federate the discipline models, detect the clashes, triage…

5 steps12 minOpen
Handover & lifecycle

Assemble the O&M handover manual

Pull together the operation and maintenance manual: collect the as-built drawings, product…

5 steps13 minOpen
Handover & lifecycle

Set up the asset register for FM

Build the asset register the operator will run the building from: capture the installed ass…

4 steps11 minOpen
Handover & lifecycle

Manage the drawing register and transmittals

Keep the drawing register under control: log every drawing and its current revision, issue…

4 steps10 minOpen
Handover & lifecycle

Raise and close a warranty claim

Get a failed asset fixed on the maker's coin: confirm it is in warranty, raise the claim ag…

3 steps7 minOpen
Handover & lifecycle

Check the asset data drop before handover

Make sure the model hands over usable asset data: read what the BIM carries, check it again…

3 steps8 minOpen
Quality & safety

Clear the snag list before handover

Drive the defects to zero before you hand over: work the open snags, re-inspect the fixes,…

3 steps8 minOpen
Quality & safety

Witness and record MEP commissioning

Prove the services actually work before handover: set the commissioning checks, witness eac…

3 steps9 minOpen
Estimating & costing

Value engineer a design to the target cost

Bring an over-budget design back to target without gutting it: find the costliest elements…

3 steps10 minOpen
Quality & safety

Run a safety walk and log observations

Catch the hazards before they hurt someone: walk the site against a checklist, raise the un…

3 steps7 minOpen
Handover & lifecycle

Draft the first year maintenance budget

Put a real number on running the building: list the assets to maintain, price their planned…

3 steps9 minOpen
Commercial & contracts

Track an opportunity from enquiry to tender

Capture the client contacts, run the opportunity through the pipeline, convert the win into…

4 steps7 minOpen
Site & field

Issue a permit to work

Raise a permit to work, tie it to its safe system of work, and close it out in the record.

3 steps7 minOpen
Quality & safety

Run the submittals register

Log shop drawings and submittals, check them against spec, issue for review, and flag anyth…

4 steps10 minOpen
BIM & takeoff

Set up the common data environment

Stand up the common data environment, load the information containers with the right status…

5 steps11 minOpen
Estimating & costing

Build the resource library and rates

Define your labour, plant and materials once, build assemblies from them, and reuse the sam…

3 steps8 minOpen
Planning & controls

Balance the portfolio and level resources

See every live project and what it demands on one board, compare that demand to the crews a…

3 steps9 minOpen
BIM & takeoff

Set up BIM requirements and coordination

Write down what information the employer actually needs from the models, set the federation…

3 steps10 minOpen
Estimating & costing

Build a 5D cost-loaded model

Start from the priced bill, link cost to the model and the programme, and tie the cost bloc…

3 steps10 minOpen
Commercial & contracts

Give the client a project portal

Open a controlled window onto the job for the client: choose what they see, show them the a…

3 steps8 minOpen
Quality & safety

Manage an engineering change

Run a design or engineering change through proper control: raise it with its reason and ris…

3 steps9 minOpen
Estimating & costing

Appraise a development scheme

Work out what a site is worth to a developer: set the scheme mix and areas, price the build…

3 steps9 minOpen
Handover & lifecycle

Run reactive FM service after handover

Handle a fault the way a building operator should: log the reactive request against the ass…

3 steps8 minOpen
Estimating & costing

Manage provisional sums and allowances

Handle the parts of a bill the design cannot yet fix - provisional sums, prime cost sums an…

4 steps10 minOpen
Estimating & costing

Escalate an estimate with price indices

Bring base-date rates forward to the midpoint of construction using published cost indices,…

4 steps9 minOpen
Estimating & costing

Build an all-in labour rate

Turn a base wage into a true cost per productive hour by adding on-costs and dividing by th…

4 steps10 minOpen
Estimating & costing

Write the basis of estimate

Capture the assumptions, inclusions, exclusions and qualifications behind a price and issue…

4 steps9 minOpen
Tendering & procurement

Level bids to a common scope

Normalise structurally different bids - filling the scope gaps and pricing the qualificatio…

4 steps12 minOpen
Tendering & procurement

Issue a tender addendum and reissue

A bidder query or a design change lands mid-tender. Capture it, draft the addendum, reissue…

4 steps9 minOpen
Tendering & procurement

Raise a subcontract order from the award

Turn a winning bid into a live subcontract order: confirm the agreed scope and rates, raise…

4 steps11 minOpen
Planning & controls

Import a programme and set the baseline

Bring an external programme in from an exchange file, check the calendars and links survive…

4 steps10 minOpen
Planning & controls

Build a 4D construction sequence

Link model elements to schedule activities, play the build order back as a 4D animation, ch…

4 steps12 minOpen
Planning & controls

Build a milestone payment schedule

Tie payment milestones to real programme events, value each one so the schedule sums back t…

4 steps10 minOpen
BIM & takeoff

Measure from a point cloud survey

Load a laser-scan point cloud of the existing conditions, measure the distances, areas and…

4 steps11 minOpen
BIM & takeoff

Run a clash profile audit

Define a clash profile - which element sets test against which, and at what tolerance - run…

4 steps12 minOpen
Site & field

Manage temporary works and inspections

Register every temporary works item, record the design check and coordinator sign-off, insp…

4 steps11 minOpen
Site & field

Mobilise the site and set up logistics

Get the site ready before work starts: run the mobilisation checklist for hoarding, welfare…

3 steps10 minOpen
Planning & controls

Manage interfaces between work packages

Build the interface register, give each interface an owner on both sides and the informatio…

4 steps10 minOpen
Commercial & contracts

Manage retention across the supply chain

Capture the retention terms both ways, track what you hold on each subcontractor, release i…

4 steps11 minOpen
Commercial & contracts

Reconcile a supplier statement

Match a supplier's monthly statement against your own purchase ledger, resolve the differen…

4 steps10 minOpen
Handover & lifecycle

Run a soft landings performance handover

Do not walk away at practical completion: confirm the in-use performance targets, set up an…

4 steps11 minOpen
Handover & lifecycle

Close out permits and statutory approvals

List every permit and planning condition, book the final statutory inspections, collect the…

4 steps10 minOpen
Quality & safety

Submit a permit package to the authority

Pull together the drawings and supporting documents an authority submission needs, build and…

4 steps12 minOpen
Quality & safety

Run an authority design review cycle

Open a review cycle against a document version, log and respond to the remarks that come bac…

4 steps10 minOpen
Handover & lifecycle

Get a key document signed off

Pick the document that needs formal sign-off, open a signing session with the right signator…

4 steps8 minOpen
Site & field

Run a site supervision visit

Plan and conduct a supervision visit, log observations and flag hidden works to inspect befo…

4 steps11 minOpen
BIM & takeoff

Adopt a CDE approval preset

Run the CDE setup wizard, adopt a ready-made ISO 19650 review flow in one click, tailor it t…

4 steps8 minOpen
Estimating & costing

Review what the AI read off the drawing

Take what the plan reader proposed on a PDF sheet and decide, proposal by proposal, what des…

4 steps12 minOpen
Quality & safety

Automate a check you keep doing by hand

Take the check you run manually every week, build it once as a pipeline from a ready-made te…

4 steps14 minOpen
Spain
Commercial & contracts

Send a bill to Spain in FIEBDC-3

Export a priced bill to FIEBDC-3, the budget format the Spanish and Latin American market ex…

4 steps11 minOpen
Site & field

Chase every overdue date in one place

Pull every due date the platform tracks into a single register, see what is genuinely late r…

3 steps9 minOpen
Site & field

Turn a document into a tracked action

Spot the letter, RFI or captured message that is asking for something to be done rather than…

3 steps8 minOpen
Site & field

See every field mark on one sheet

Open one drawing and see every mark the project has recorded against it, punch pins, plan pi…

4 steps7 minOpen
Estimating & costing

Build a parametric assembly

Give an assembly named parameters and drive its component quantities from formulas over them…

4 steps12 minOpen
Germany
Commercial & contracts

Issue a compliant XRechnung

Turn a period of finished work into an electronic invoice a German public client will actual…

7 steps11 minOpen
Germany
Tendering & procurement

Build a Preisspiegel and award

Send one work package to several Nachunternehmer, level what comes back onto the same scope,…

7 steps13 minOpen
Germany
Commercial & contracts

Soll-Ist control on a running site

Read the Deckungsbeitrag while the site is still running: set the Soll from the calculation,…

7 steps14 minOpen
Germany
Site & field

Keep a court-proof Bautagebuch

Write the site day while it happens - weather from an independent source, crews, progress, o…

6 steps11 minOpen
Germany
Commercial & contracts

Run the VOB/B payment clock

Register the contract, raise each Abschlagsrechnung against it, open a payment clock over th…

7 steps12 minOpen
Russia
Tendering & procurement

Bid a state contract under 44-FZ

Read the notice to settle whether 44-FZ or 223-FZ governs, rebuild the NMCK from the custome…

7 steps15 minOpen
Russia
Site & field

Reconcile materials on form M-29

Take the norm consumption for the work the month actually completed, set it against what the…

7 steps14 minOpen
Australia
Commercial & contracts

Price a variation under AS 4000

Establish that there is a direction before anyone builds it, keep the cost record while the…

6 steps16 minOpen